Task Definition Glossary

Title

The name of the task to be completed.

Order

If there is more than one task, in what order should they be completed?

Estimated hours

We are not currently using Time & Expense functionality in TeamDynamix; leave it at 0.

Complete Within

We are not currently tracking Service Level Agreements; set to 0.

Predecessor

If a task has a predecessor, it will not show as Assigned until the predecessor has been marked as completed.

Responsible

If the task has an assigned responsible party, select the user/group here.

Description

The description of the task to be completed.

 

Print Article